Project Status 08/04/14

posted Aug 5, 2014, 9:56 AM by Lebanon NH   [ updated Aug 6, 2014, 5:54 AM ]
Over the past 5 weeks, all tree clearing has been completed. The cofferdam for pier 2 of the new bridge has begun, and footing excavation should begin in about 2 weeks. The relocated Route 4/4A (west side) earth cut began last week and is expected to be ready in approximately 6 weeks. Once done, Liberty Utilities will begin setting new poles. 

A cofferdam is a watertight enclosure from which water is pumped to expose the bottom of a body of water to permit construction (such as a pier)