All updates relating to the Route 4/4A Bridge Project will be posted chronologically on this page as they become available. Scroll down the page to review previous updates. 

Rail Trail Closure 06/02/15

posted Jun 1, 2015, 1:04 PM by Lebanon NH   [ updated Jun 1, 2015, 1:08 PM ]

cone
On Tuesday, June 2, 2015 the Rail Trail under the US Route 4 bridge will be closed for a few hours sometime between 7:00 AM and NOON. The Mill Road to Ice House Road trail detour will be activated in order to adequately move people around the work zone. 

 Thank you for your patience. 

Project Update 05/11/15

posted May 11, 2015, 12:04 PM by Lebanon NH   [ updated May 11, 2015, 12:07 PM ]

During the next 2 weeks, bridge structural steel erection will be taking place on a daily basis at the US Route 4 bridge project over the Mascoma River located at the intersection of NH 4A in Lebanon, NH. For safety reasons the traffic on Route 4 will be stopped for approximately 10 to 15 minutes sometime between 5:30 AM - 6:00 AM daily while the beams are being lifted near traffic. A similar delay will occur daily sometime during the late morning, after commuter hours.

Also beginning on Monday, May 18th, for about 2 weeks the section of the NH Rail Trail under the bridge will be closed due to various overhead construction hazards. A rail trail detour will be in place with signs directing trail users around the work via Mill Road, across Route 4, then along NH 4A to Payne Road, then following Route 4 for a few hundred feet to Ice House Road and returning back to the Rail Trail. The trail will be not be closed during non work hours and weekends.

The project replaces the existing structurally deficient bridge and involves road realignment on US Rte 4 and NH 4A with safety and environmental improvements. The NHDOT contract was awarded to the low bidder, RS Audley Construction from Bow NH for a total 8.9 million dollars. The project is 80% federally funded with 20% state matching funds.

For more information please contact NHDOT contact listed below.

Peter M. Kehoe, P.E.
NHDOT Contract Administrator
Lebanon 13951 Bridge Project
603-491-7291

Project Status 08/04/14

posted Aug 5, 2014, 9:56 AM by Lebanon NH   [ updated Aug 6, 2014, 5:54 AM ]

Over the past 5 weeks, all tree clearing has been completed. The cofferdam for pier 2 of the new bridge has begun, and footing excavation should begin in about 2 weeks. The relocated Route 4/4A (west side) earth cut began last week and is expected to be ready in approximately 6 weeks. Once done, Liberty Utilities will begin setting new poles. 

A cofferdam is a watertight enclosure from which water is pumped to expose the bottom of a body of water to permit construction (such as a pier)

Please direct questions about the Route 4/4A Bridge Project to:

Peter M. Kehoe
NHDOT Contract Administrator
Lebanon 13951
603 491-7291
pkehoe@dot.state.nh.us


Design Plans & Bid Date

posted Dec 6, 2013, 8:23 AM by Lebanon NH   [ updated Dec 6, 2013, 8:23 AM ]

The City has received 60% design plans and this project is slated to bid in August 2014. 