CSO #10 Update & Advertisement for Bids

posted Sep 26, 2014, 5:32 AM by Lebanon NH   [ updated Sep 26, 2014, 5:34 AM ]

CSO10
The City of Lebanon has posted an Advertisement for Bids for Combined Sewer Separation - Contract No. 10 – which encompasses all or portions of seven streets including full depth pavement reconstruction, sewer utilities, water utilities, storm drainage utilities, pavement overlays, retaining walls and other related appurtenances.
CSO #10 involves the separation of storm water and sewer lines along with replacement of water lines. The Department of Public Works is responsible for a large part of the public health/safety sector with respect to the drinking water of the city. Many residents don’t often think of what goes on underneath the street that pertains to their health.

In the latest episode of Lebanon in Depth, City Manager Greg Lewis discussed a few of Lebanon's construction projects with Public Works Director Mike Lavalla, Assistant Public Works Director Bruce Temple and City Engineer Christina Hall. 

CSO #10 Final Design Plans

posted Jul 9, 2014, 12:05 PM by Lebanon NH   [ updated Jul 9, 2014, 12:14 PM ]

The City of Lebanon Public Works Department has posted Final Design Plans for the CS0 10 Project. 
Please contact the Public Works Department at 603-448-3112 if you have have questions or concerns. 

CSO #10 Informational Meeting

posted Apr 1, 2014, 12:24 PM by Lebanon NH   [ updated Apr 1, 2014, 12:24 PM ]


Please join us this evening at the Kilton Public Library Community Room beginning at 6:30 pm for an informational meeting and presentation of Combined Sewer Overflow (CSO) Project, Phase 10.
Representatives from Public Works and consultant Wright-Pierce will be present to give a short overview of the design of the streets within the CSO #10 area (Green Street West, Winter Street West, Dana Street (from North Main Street to Prospect Street West), Timothy Avenue, Pearl Street, Prospect Street, North Main Street and Highland Avenue.)

If anyone has any questions regarding this meeting please contact Public Works at 603-448-3112. 

Posted by the Public Works Department.

Conceptual Plans & Presentation

posted Oct 29, 2013, 9:35 AM by Lebanon NH   [ updated Oct 29, 2013, 9:40 AM ]



Neighborhood Meeting

posted Oct 29, 2013, 8:10 AM by Lebanon NH   [ updated Oct 29, 2013, 8:10 AM ]

On Wednesday, October 23rd at 7PM, a neighborhood meeting will be held in the Community Room at the Kilton Library in West Lebanon. The meeting will be used to solicit input from residents regarding the design features of the upcoming Combined Sewer Overflow (CSO) Project Phase 10. 

 Streets that will be affected by this project include: Green Street West, Winter Street West, A small portion of Dana Street (from North Main to Prospect Street), Timothy Avenue, Pearl Street, Prospect Street West, North Main Street, and Highland Avenue. 

Representatives from the City, along with the city’s consultant Wright-Pierce, will be available to answer questions and provide a brief overview of the project.

CSO Phase 10 Walkabout Notice

posted Oct 29, 2013, 8:08 AM by Lebanon NH   [ updated Oct 29, 2013, 8:09 AM ]

The following notice was sent to property owners living in the CSO Contract 10 area. Affected streets include: Green Street West, Winter Street West, Dana Street (from North Main to Prospect Street), Timothy Avenue, Pearl Street, Prospect Street West, North Main Street (from Estabrook Circle to Dana St.), Highland Avenue.

On Saturday, June 15, 2013 beginning at 1:00pm City Staff will be conducting an on-street meeting to review possible impacts to individual properties. Please read the official release for complete details.

CSO Phase 10 Surveying Notice

posted Oct 29, 2013, 8:06 AM by Lebanon NH   [ updated Oct 29, 2013, 8:06 AM ]

Beginning Monday, May 20, 2012, survey crews from Millennium Engineering, Inc. will be working to identify and mark the City’s Right-of-Way (ROW) on the above referenced streets as we move into the design process for CSO Contract 10. 